HomeProjects

Tangenvika railway bridge

See how Norway's longest railway bridge is being built

The Tangenvika railway bridge is currently being built over Lake Mjøsa. Welding of the enormous pile tubes for the foundation of the bridge is being done by Nordic Steel.

- Keller Geoteknikk AS has chosen Nordic Steel as its supplier to weld steel piling pipes for the Tangenvika project. The pipes are up to 1.4 meters in diameter and 85 meters long. "The welding must follow strict execution procedures and tolerances, as the pipes are components of the bridge foundation," explains Wojciech Szczepinski, project manager at Keller.

Welding coordinator at Nordic Steel, John-Christian Bruntveit, follows production in Tangenvika closely.

Very high level of welding technology

Since August 2023, Nordic Steel has had a base for welding technical personnel and performed complex and specialized welding at the construction site in Tangenvika.

- "We've optimized a production hall in Tangenvika for advanced, mechanized welding of pile pipes. Here we use an automated welding process that ensures quality and accuracy," explains Torjus Ulsaker, Head of Construction at Nordic Steel.

John-Christian Bruntveit is one of Nordic Steel's welding coordinators, and has worked permanently at the Tangenvika plant for the past year. He emphasizes the close follow-up on welding: "All welding is checked and followed up by our welding engineers.

The construction area in Tangenvika. Photo: Keller Geoteknikk AS

Double track on the railway

The construction of a railway bridge over Lake Mjøsa is a complex and exciting construction project that will have the least possible impact on the environment in and around Lake Mjøsa.

When the project is completed, it will be a major boost for climate-friendly travel and freight traffic between Oslo and Hamar.

- We at Keller are pleased that we can work on this project with highly experienced and competent employees from Nordic Steel, and that the work will be delivered to the required standards," says Wojciech Szczepinski.

Pile pipe outside the production hall in Tangenvika. Photo: Keller Geoteknikk AS
The piles are up to 85 meters long. Photo: Keller Geoteknikk AS
The production hall for pile pipes. Photo: Keller Geoteknikk AS
Quantities of piling pipes in Tangenvika. Photo: Keller Geoteknikk AS

Facts about the project

  • Bane Nor is the developer of the double track through Stange municipality
  • Implenia has the turnkey contract for KS-2 Tangenvika railway bridge
  • Keller Geoteknikk AS performs foundation work
  • The double track provides more departures, shorter travel times and increased capacity for freight transport between Oslo and Hamar
  • In total, there are 29.7 kilometers of double track
  • The bridge over Tangenvika is 1026 meters long
  • The project will be completed by the end of 2027

We at Keller are pleased that we can work on this project with highly experienced and competent employees from Nordic Steel, and that the work will be delivered to the required standards.

Wojciech Szczepinski
Keller Geotechnikk AS

Other projects we have carried out.

Sign up for our newsletter